Deployment will be subject to fulfilment of System Acceptance Criteria outlined below:

The application will be considered suitable for acceptance if it delivers the functionality as outlined in the 'Features and Functionalities' document that will be signed off on completion of the Design Phase.

The application has to meet two important criteria :

Completeness
The 'Completeness' of the application will be determined by checking the functionality of the delivered software with the scope document agreed to
Correctness
The 'Correctness' of the application will be determined through User Acceptance Testing. The bugs identified during this process will be prioritized based on the following guidelines:

Priority 1 - Show Stopper - there is no work around
Priority 2 - Critical - Work around exists but is not acceptable
Priority 3 - Moderate - Work around exists and is acceptable
Priority 4 - Cosmetic- with minor changes required

All Priority 1 and Priority 2 bugs will be fixed during the warranty period, failing which the warranty period automatically stands extended.